Musaimeer Pumping Station & Outfall Tunnel

Project

Design & Construction of Musaimeer Pumping Station and Outfall Tunnel.

Client

Public Works Authority – Ashghal

Consultant

Mott MacDonald Limited

Contractor

HBK-PORR JV

LEED Typology

CEEQUAL Version 5 – Design & Construction Assessment

Scope

CEEQUAL Facilitation for Design & Construction Stage .

Achieved certification

Very Good

Description

Conserve has been appointed by M/s HBK-PORR JV to facilitate Design & Construction Stage CEEQUAL Assessment from design documentation to final certification. The project comprises of a pumping station be able to handle a peak flow 19.7 m3/s with a 3.7m diameter marine outfall tunnel for 10 Km and an offshore riser shaft and 84 port diffuser field. The project was delivered with excellence in Sustainability performance becoming first project in Qatar achieve “Very Good” rating.