Which of the subsequent project team member(s) is usually responsible for developing the erosion and sedimentation control (ESC) plan for construction activity pollution prevention?

A) The project owner(s)
B) The civil engineer(s)
C) The LEED AP
D) The architect(s)

Answer

The right answer is B 

This question is associated with Prerequisites 1: Construction Activity Pollution Prevention.

To comply with the prerequisite

The civil engineer is usually responsible for the plan. The landscapist or general contractor may fit on the plan’s development. The project owner, the LEED AP and also the architect mostly won’t be liable for developing Erosion and sedimentation control.